MAJOR WORKS: ENGINEERING ( 1- INDUSTRY, ENERGY AND MINING ):
· Crushing, conveying and sizing MINING MACHINERY design. Clients: Trame and Canteras El Sierro.
· White marble GRINDING PLANT at Macael ( Almería ), 100.000 Tm/year: first draft.
· INDUSTRIAL BUILDING devoted to skin treatment at Huecas ( Toledo ), property of Pieles García Rico, 750 m²: project.
· INDUSTRIAL BUILDING at Ocaña ( Toledo ), property of Uniarte, 65,000 m² ( 700,000 sq.ft. ): project.
· Milan Sud ( Italy ) sewage treatment plant, maximum flow 775,000 m³/day: collaboration in MUD DEHYDRATION and DRYING plant design.
· Process and equipment design for quarry waste WATER TREATMENT PLANT at Peñas de San Pedro ( Albacete ), flow 50 m³/h.
· DISTRIBUTION CENTER for Logista, formed by 23,000 m² of warehouse and 4,000 m² of office building at Leganés (Madrid): electrical / lighting, emergency power generation and IT cabling design.
· DISTRIBUTION CENTER for Riofisa, formed by 15,000 m² of warehouse and 400 m² of office building at S. Agustín de Guadalix ( Madrid ): electrical / lighting, IT cabling, fire protection, HVAC and plumbing systems design.
· Cecauto DISTRIBUTION CENTER at S. Boi del Vallés ( Barcelona ), 5,000 m² of warehouse and 1,700 m² of office building: electrical / lighting, IT cabling, fire protection, HVAC and plumbing design.
· DISTRIBUTION CENTER for Redur, formed by 22,900 m² of warehouse and 800 m² of office building at Algete ( Madrid ): fire protection system design.
· Industrial buildings in Redur DISTRIBUTION CENTER, Algete ( Madrid ), 6,100 m²: electrical / lighting, IT cabling, fire protection, HVAC and plumbing systems design.
· High speed train TUNNELS at Guadarrama ( 2 x 28 km, 2 x 18 miles ): fire extinction system design.
· Feasibility studies for 5, 18 and 50 kWp PHOTOVOLTAIC POWER PLANTS at Madrid and Palma de Mallorca.
· Collaboration in projects for 40 and 50 kWp PHOTOVOLTAIC POWER PLANTS at Aranjuez and Torrejón de Ardoz, Madrid.
Other works:
· Adeje-Arona ( Tenerife ) sea water DESALINATION PLANT, pure water flow 10.000 m³/day: assembly and installations project management; employee in SPA firm.
· Oily waste WATER TREATMENT PLANT in the Candelaria fuel power plant (Tenerife) : project management; employee in SPA firm.
· Maintenance works at Cofrentes nuclear POWER PLANT and at Valdecañas hydroelectric power plant; employee in NIP firm.